A quoted lead time is not a delivery date. When a supplier says “20–35 days”, that is almost always the time to build, test and prepare the machine for shipment. It does not include the ocean crossing or your customs clearance. The total time to your site is usually two to three times longer, and many import projects fail on that difference.
The four blocks that make up the real total
| # | Block | What happens | Biggest variable |
|---|---|---|---|
| 1 | Preparation | Order confirmed, unit built or taken from stock, tested, packed | In stock or built to order |
| 2 | Inland transport and booking | Transport to the port, container booking, loading, export clearance | Sailing frequency on your route |
| 3 | Ocean transit | Port to port | Destination port; direct or transshipped |
| 4 | Arrival | Customs clearance, duties, delivery to site | Document quality; your customs broker |
Block 1 is the only one most quotations describe. Blocks 2 to 4 usually take most of the calendar time, and block 3 alone is often the longest single stage.
Where the confusion starts
Most quotations state lead time in the standard way: lead time 20–35 days after deposit, confirmed per order. Read literally, that is block 1. Buyers who read it as “it arrives in a month” are not careless. The phrase sounds like a delivery promise, and few suppliers explain that it is not.
Ask for two dates, not one: the ready-to-ship date and the estimated arrival at your port. A supplier who can give only the first has not checked your route.
What changes the total
Shortens it:
- A model held in stock in a standard voltage and frequency configuration
- A full container rather than a shared one, because consolidation adds waiting time
- Documents prepared correctly the first time
- A destination port with direct sailings
Lengthens it:
- Any non-standard configuration. A different voltage, frequency, alternator or control panel usually moves the unit from “in stock” to “built to order”
- Transshipment, where your container changes vessel at an intermediate port
- Peak season and factory holidays, which affect both production and space on vessels
- Missing or inconsistent documents at the destination. Of the four blocks, this is the most common delay that could have been avoided
The figure no one can give in advance
Ocean transit time depends more on the destination and routing than on anything the supplier controls. Two ports on the same coast can differ by weeks if one has direct sailings and the other is served through a transshipment port. For this reason, a general “shipping takes about X weeks” figure on a website says very little.
Ask for the transit time to your named port, and ask whether the routing is direct. Those two answers turn a vague range into a date you can plan around.
What to ask before you commit
A competent supplier can answer these five questions in one reply:
- Is this exact model in stock, or built to order? This answer alone often decides whether block 1 takes days or weeks.
- From when is the lead time counted: from the deposit clearing, or from order confirmation?
- Which port are you quoting to, and is the routing direct or transshipped?
- Which Incoterm? EXW, FOB and CIF set the handover point in different places. That changes who is responsible for blocks 2 to 4, and so who bears the cost of a delay.
- Which documents will I receive, and when? Late documents cause customs delays, and you pay for the storage.
Plan backwards from your date
If you need power running by a fixed date, such as a harvest, a project handover or a season, count backwards from that date, not forwards from the order. Estimate the four blocks, add a buffer for the one you control least (block 3), and set your order date from there.
Two tasks can run at the same time instead of one after the other. Settle the model early, because choosing the wrong size late forces a new quotation and can move a stock unit to built-to-order. Prepare the site while the unit is at sea: the foundation, ventilation and exhaust do not need the machine to be present.
Where HTX fits
We state lead time in the standard way, as days after deposit, and by it we mean block 1. Tell us your destination port, and we will send the transit estimate for that routing, together with which of our models are available from stock and which need a production slot. If the total does not fit your date, we will tell you before you pay the deposit.
Bidding on a tender? The tender fixes the delivery date, and some required documents take several working days to prepare. Our tender page lists what to send us so we can check the specification and confirm the documents before you submit.
Working to a fixed date? Send us the date you need power running, your destination port and the load you are covering, or message us on WhatsApp. Our engineers will reply within 24 business hours with a realistic total, block by block.